DHMSCare caught early misalignment on a coal-fired power station's secondary fan, and the plant avoided an unplanned shutdown.

Fujian Energy & Petrochemical Group operates the coal-fired power station in this case. DHMSCare monitors the secondary fan of its Furnace No. 3 and auxiliary pumps elsewhere in the plant.
A coal-fired power station runs around the clock, and its fans and pumps must keep running for each boiler to stay online. When a key fan stops without warning, the boiler it serves can be forced out of service.
Manual meter reading and inspection rounds took much of the team's time, and environmental compliance reports took many person-days every month.
A fault that develops between two rounds can go unseen until it forces a stop.



DHMSCare flags early misalignment on the secondary fan of Furnace No. 3
Rising vibration and the vibration pattern typical of misalignment appeared together
The plant acted in time
An unplanned shutdown was avoided
Vibration trend
Spectrum pattern
DHMSCare flagged early misalignment on 7 January 2025, eight days before it turned severe, after rising vibration and the vibration pattern typical of misalignment agreed. The plant acted in time and avoided an unplanned shutdown.
The plant reported that unplanned shutdowns fell by 65%, from 5.6 to 2 per year, and that the mean time to repair fell from 4.5 hours to 1.2 hours.
The plant reported 70% less manual meter reading and inspection work, and about 20 person-days a month saved on environmental compliance reporting.